Karla's Studio-Shed Project!
< back to sirwatson.com
Thanks for visiting my studio construction page! Here, I'll keep everyone posted on the progress related to my shed-studio. Select one of the links below to view my progress over the specific time period (I had to break the days up since the original page took way too long to download with all the images).

Once the studio is finished being built, I'll be scheduling a "shed-ication" to help commemorate my new studio! :)
  • The Finished Studio! Updated 5/08/07!
  • Days 35-36 (propane & ventilation) Updated 5/07/07!
  • Days 31-34 (flooring & trim)
  • Days 26-30 (taping/mudding walls, painting)
  • Days 21-25 (insulation and drywall)
  • Days 16-20 (electrical wiring)
  • Days 14-15 (begin inside work: painting rafters, installing electrical outlets and wiring)
  • Days 10-13 (installing windows and door, finishing trim and staining)
  • Days 7-9 (felting the roof, adding shingles and starting on trim)
  • Days 4-6 (erecting the walls, installing rafters and roof boards)
  • Days 1-3 (arrival of the shed-kit, framing the floors and walls)